Start meter upgrade
This Task is:
- if the Site's state is Victoria, triggered for on-app and off-app Jobs when the Upload Regulatory Documents Task is completed.
- if the Site's state is not Victoria, triggered:
- for on-app Jobs when the Installer has submitted all forms in-app.
- for off-app Jobs when Upload Commissioning Sheet and Photos Task is completed.
- in parallel with Review Installation Artefacts Task and Confirm Monitoring Setup Task.
- done by Prime Operations.
This is a prompt to begin activities required to upgrade the Customer's meter. This Task must be completed before the Installation Job status will update to Commissioned.
Next task
If the following tasks are also completed, the next Task for on-app and off-app Jobs is Generate Customer Invoice.
- Confirm Monitoring Setup.
- Upload STC Assignment Form.
- Update Asset Serial Numbers.
- Upload Regulatory Documents, if the Site not in Victoria.
Steps
- Initiate the Customer's meter upgrade process.
- Click Complete.