Installation jobs
Job pack
The Job pack for an Installation includes:
- Install Job Info Sheet - this contains system details and notes from UPowr.
- Site Inspection Report.
- Single Line Diagram.
- Permission to Connect.
- Bill of Materials.
- Leave Behind Pack.
- Photos: Site layout and switchboard.
Tasks
Installation jobs consist of four Tasks:
- Pre-installation checklist
- Roof works installation
- System installation
- Commissioning sheet
1 - Pre-installation checklist
Purpose
Ensure site walk-around and set-up procedures have been completed correctly and safely.
Sign-off
Must be signed off and submitted by a CEC-accredited Lead installer.
Timing
Must be submitted before any Installation work begins.
2 - Roof works installation
Purpose
Provide evidence that racking, PV modules, and roof cavity works (including labelling) are completed in accordance with regulatory requirements and the UPowr Standard of Works.
Note: not required for battery-only jobs.
Sign-off
Must be signed off and submitted by a CEC accredited team lead on Installation day.
Timing
- Racking installation section must be completed after installing all rails, cabling, and roof penetration point(s) and before installing modules.
- PV modules section must be completed when all rooftop installation work is done.
- Roof cavity section must be completed when the conduit installation inside the roof cavity is done (note: skipped if no roof cavity works are required).
3 - System installation
Purpose
Collect asset details and ensure the system has been installed and labelled in accordance with regulatory requirements and the UPowr standard of works.
Sign-off
Must be signed off and submitted by a CEC accredited team lead on Installation day.
Timing
Completed after inverter or battery unit(s) and associated components have been installed and labelled, and switchboard changes are done.
4 - Commissioning sheet
Purpose
- Compete CEC-required commissioning and testing procedures to ensure the system is installed correctly and operational.
- Ensure customer handover procedures have been completed.
Sign-off
Must be signed off and submitted by a CEC accredited installer and Licensed electrician on Installation day.
Timing
Completed once the system is installed and ready to be commissioned.