Receive order confirmation from supplier | Removed as it wasn't used |
Calculate voltage rise | Removed and its functionality added to Review installation artefacts task |
Complete monitoring | Trigger is now once the Job is submitted. This task must be completed for the Installation Job status to become Commissioned. We also added the Assets on the Site to the Task, to help Operators identify the relevant Assets in the monitoring portal. |
Complete meter upgrade | Replaced with the Start meter upgrade Task. This Task is triggered for Sites not in Victoria when the job status is Submitted, and Sites in Victoria when the Upload regulatory documents task is completed. |
Upload STC assignment form, Upload regulatory documents, and Update asset serial numbers | These three tasks are now triggered simultaneously when the job status is updated to Reviewed. |
Update asset serial numbers | Now includes all Assets on the Site so operators can check inputs provided by the Installer via the App. |
Assign Installation to Installer and App | Now includes Jobs related to a Project so the Operator knows which Installer company completed any previous Jobs |
Select Tasks across the Workflow | We added the Job files component so the Operator can verify information using artefacts such as the Site inspection report. |